Bluespace - Valencia, Spain
Project Overview
Project type: Internal Fit Out
 
Client
Bluespace, Spain
 
Site
Alfafar, Valencia, Spain
 
Site Specs
Gross Block Area: 8000m2
Gross Floor Area: 4120m2
Net Lettable Area: 2199
Number of units: 421
Stages: 3
 
Processes handled by Steel Storage
Site analyses
Facility design layout
Feasibility study
Consultant co-ordination
Design and Construct
Internal high partitioning
Gloss White hallway panelling
 
Special Features
4 level structure
 
Learning Experience
Access was difficult as building had steps to front and a narrow ramp down to the basement. Inside were stairs and intermediate levels. After consultation with client it was decided that a ramp would be built to access the front of the building and the ramp to the basement would be retained. The basement was designed with large units for commercial customers using the retained ramp as designated access and a turning and unloading area was designed in the basement. 2 lifts were installed by client to allow access to 1st intermediate and 2nd floors.
 
1. INTERNAL PARTITIONING
Dividing Security Partitioning All internal walls are constructed using our patented vertical interlocking, high security SS810 “Guardian” Safe Edge panel system. The panels are roll formed using resin coated steel. The partitions are set into 1.2mm Zincalume(R) channel tracks top and bottom, with vertical channel at intersecting points. Exposed edges are protected by safety edges to all return folds and there are no vertical fixings, pop rivets or studwork requirements.
 
2. PHASE ONE COMPLETE
Here is a final photo of Phase 1 Ground and basement complete showing the ramp access to the front entrance. The site has been fully fenced for security purposed along with state of the art CCTV, PTI unit alarming and access control. Easy access from the road frontage feeds clients directly into the reception area of the office complex allowing the on site Storage Consultant and Facility Manager not only to receive new clients but to also monitor facility traffic.  
 
3. PHASE TWO UNDER CONSTRUCTION
 
 
 
The finished Facade 
 
 
1st Floor, Prior to fit-out 
 
 
After Fit-out